Running a Job task in a Data Plane environment manually

Availability-noteBeta

Your task is processed by the Data Plane connected to the environment, selected during the task creation.

You cannot run a task if the Data Plane and its environment are not connected.

The task cannot be processed by a Data Plane connected to an environment with the Connecting, Not connected or Error status.

Before you begin

  • You must have the Execute permission on the workspace where the task is located to run a Job task.
  • The Data Plane and its environment must be connected (Connected status).

Procedure

  1. Open the Management page.
  2. Go to the Tasks tab.
  3. Select the task from the list.
    You can use the filters at the top of the page for example by selecting the environment, the workspace and the task type.
  4. From the task details page, click Run now to execute your task.
  5. Go to the Operations page to monitor its status.
  6. Click the task name to open the Run overview page.
  7. Open the Logs tab to see the task run logs.
  8. Open the Job tab to see the task design and run configuration.
  9. Expand the right panel to see the task parameters.
  10. Click View run history under Run ID to access the run history of the task.

Did this page help you?

If you find any issues with this page or its content – a typo, a missing step, or a technical error – let us know how we can improve!