Skip to main content Skip to complementary content

Running a plan in a Data Plane environment manually

Availability-noteBeta

Your plan is processed by the Data Plane connected to the environment, selected during the plan creation.

You cannot run a plan if the Data Plane and its environment are not connected.

The plan cannot be processed by a Data Plane connected to an environment with the Connecting, Not connected or Error status.

Before you begin

  • You must have the Execute permission on the workspace where the plan is located to run a plan.
  • The Data Plane and its environment must be connected (Connected status).

Procedure

  1. Open the Management page.
  2. Go to the Plans tab.
  3. Select the plan from the list.
    You can use the filters at the top of the page for example by selecting the environment and the workspace.
  4. From the plan details page, click Run now to execute your plan.
  5. Go to the Operations page to monitor its status.
  6. Click the plan name to open the Plan run history page to see more details about the plan execution.

Did this page help you?

If you find any issues with this page or its content – a typo, a missing step, or a technical error – let us know how we can improve!