Follow these steps to create the last Job, which will display the results of access log analysis.

Procedure

  1. Create a new Job and name it F_Read_Results to identify its role and execution order among the example Jobs.
  2. From the Palette, drop two tHDFSInput components and two tLogRow components onto the design workspace.
  3. Link the first tHDFSInput to the first tLogRow, and the second tHDFSInput to the second tLogRow using Row > Main connections.
  4. Link the first tHDFSInput to the second tHDFSInput using a Trigger > OnSubjobOk connection.
  5. Label the components to better identify their functionality.